This project is intended to enhance intersection safety for pedestrians crossing Moores Pike at the Clarizz Blvd intersection.

Project Map:

Site Map

Project Description:

Funding for design is provided through the Common Council Sidewalk Committee. This project is intended to enhance intersection safety for pedestrians crossing Moores Pike at the Clarizz Blvd intersection.

Project Timeline:

  • Design: 2017-2018
  • Construction:  early 2019

Quote Documents:

Quote Results:

  • Milestone Contractors, LP  $151,178.50

  • E&B Paving, Inc.                    $139,730.00 (Awarded)

 

Project Contact:

Russell White
(812) 349-3423 or whiter@bloomington.in.gov