This maintenance project will include asphalt maintenance, accessible sidewalk curb ramps, minor curb modifications, and restriping.

Construction funding is provided by the Community Crossings Matching Grant program.

Project Timeline:

  • Design: Spring 2023
  • Construction: Summer/Fall 2023.

Bidding Documents:

Letting Date: March 13th, 2023

 

Zoom meeting link for Bid Opening- Click here

 

Bids are due in the City Hall Atrium by 11:50 AM on Monday, March 13th, 2023.  Bids will be opened and read aloud at a public meeting, City Hall, 401 North Morton Street at 12:00 PM (Noon) on Monday, March 13th, 2023.  

 

Bid Results: 

Milestone Contractors, LP - $474,712.00

E & B Paving, LLC - $549,300.00

 